2. Excavation for foundations
3. Foundation constructed e.g. concrete poured.
4. Damp Proof Course laid.
5. Oversite ready for concreting (with damp proof membrane laid if appropriate).
6. Drains laid and visible for checking layout and construction.
7. Drains backfilled and ready for testing for water tightness.
8. Occupation (normally only relevant when part of a building is finished e.g. a flat)
9. Completion of the whole job.
These inspections are not necessarily the only ones your Building Control Surveyor will make. Some jobs will require extra specific inspections such as reinforcement of concrete structures and fire protection to the structure. In addition to these he may call at other times to check on the work in progress